Hazard and operability study

(Redirected from HAZOP)

A hazard and operability study (HAZOP) is a structured and systematic examination of a complex system, usually a process facility, in order to identify hazards to personnel, equipment or the environment, as well as operability problems that could affect operations efficiency. It is the foremost hazard identification tool in the domain of process safety. The intention of performing a HAZOP is to review the design to pick up design and engineering issues that may otherwise not have been found. The technique is based on breaking the overall complex design of the process into a number of simpler sections called nodes which are then individually reviewed. It is carried out by a suitably experienced multi-disciplinary team during a series of meetings. The HAZOP technique is qualitative and aims to stimulate the imagination of participants to identify potential hazards and operability problems. Structure and direction are given to the review process by applying standardized guideword prompts to the review of each node. A relevant IEC standard[1] calls for team members to display 'intuition and good judgement' and for the meetings to be held in "an atmosphere of critical thinking in a frank and open atmosphere [sic]."

The HAZOP technique was initially developed for systems involving the treatment of a fluid medium or other material flow in the process industries, where it is now a major element of process safety management. It was later expanded to the analysis of batch reactions and process plant operational procedures. Recently, it has been used in domains other than or only loosely related to the process industries, namely: software applications including programmable electronic systems; software and code development; systems involving the movement of people by transport modes such as road, rail, and air; assessing administrative procedures in different industries; assessing medical devices; etc.[1] This article focuses on the technique as it is used in the process industries.

History

edit

The technique is generally considered to have originated in the Heavy Organic Chemicals Division of Imperial Chemical Industries (ICI), which was then a major British and international chemical company.

Its origins have been described by Trevor Kletz,[2][3] who was the company's safety advisor from 1968 to 1982. In 1963 a team of three people met for three days a week for four months to study the design of a new phenol plant. They started with a technique called critical examination which asked for alternatives but changed this to look for deviations. The method was further refined within the company, under the name operability studies, and became the third stage of its hazard analysis procedure (the first two being done at the conceptual and specification stages) when the first detailed design was produced.

In 1974 a one-week safety course including this procedure was offered by the Institution of Chemical Engineers (IChemE) at Teesside Polytechnic. Coming shortly after the Flixborough disaster, the course was fully booked, as were ones in the next few years. In the same year the first paper in the open literature was also published.[4] In 1977 the Chemical Industries Association published a guide.[5] Up to this time the term 'HAZOP' had not been used in formal publications. The first to do this was Kletz in 1983, with what were essentially the course notes (revised and updated) from the IChemE courses.[2] By this time, hazard and operability studies had become an expected part of chemical engineering degree courses in the UK.[2]

Nowadays, regulators and the process industry at large (including operators and contractors) consider HAZOP a strictly necessary step of project development, at the very least during the detailed design phase.

Method

edit

The method is applied to complex processes, for which sufficient design information is available and not likely to change significantly. This range of data should be explicitly identified and taken as the "design intent" basis for the HAZOP study. For example, a prudent designer will have allowed for foreseeable variations within the process, creating a larger design envelope than just the basic requirements, and the HAZOP will be looking at ways in which this might not be sufficient.

A common use of the HAZOP is relatively early through the detailed design of a plant or process. However, it can also be applied at other stages, including later operational life of existing plants, in which case it is usefully applied as a revalidation tool to ensure that unduly managed changes have not crept in since first plant start-up. Where design information is not fully available, such as during front-end loading, a coarse HAZOP can be conducted; however, where a design is required to have a HAZOP performed to meet legislative or regulatory requirements, such an early exercise cannot be considered sufficient and a later, detailed design HAZOP also becomes necessary.

For process plants, identifiable sections (nodes) are chosen so that for each a meaningful design intent can be specified [citation needed]. They are commonly indicated on piping and instrumentation diagrams (P&IDs) and process flow diagrams (PFDs). P&IDs in particular are the foremost reference document for conducting a HAZOP. The extent of each node should be appropriate to the complexity of the system and the magnitude of the hazards it might pose. However, it will also need to balance between "too large and complex" (fewer nodes, but the team members may not be able to consider issues within the whole node at once) and "too small and simple" (many trivial and repetitive nodes, each of which has to be reviewed independently and documented).

For each node, in turn, the HAZOP team uses a list of standardized guidewords and process parameters to identify potential deviations from the design intent. For each deviation, the team identifies feasible causes and likely consequences then decides (with confirmation by risk analysis where necessary, e.g., by way of an agreed upon risk matrix) whether the existing safeguards are sufficient, or whether an action or recommendation to install additional safeguards or put in place administrative controls is necessary to reduce the risks to an acceptable level.

The degree of preparation for the HAZOP is critical to the overall success of the review. "Frozen" design information provided to the team members with time for them to familiarize themselves with the process, an adequate schedule allowed for the performance of the HAZOP, provision of the best team members for their role. Those scheduling a HAZOP should take into account the review scope, the number of nodes to be reviewed, the provision of completed design drawings and documentation and the need to maintain team performance over an extended time-frame. The team members may also need to perform some of their normal tasks during this period and the HAZOP team members can tend to lose focus unless adequate time is allowed for them to refresh their mental capabilities.

The team meetings should be managed by an independent, trained HAZOP facilitator (also referred to as HAZOP leader or chairperson), who is responsible for the overall quality of the review, partnered with a dedicated scribe to minute the meetings. As the IEC standard puts it:[1]

The success of the study strongly depends on the alertness and concentration of the team members and it is therefore important that the sessions are not too long and that there are appropriate intervals between sessions. How these requirements are achieved is ultimately the responsibility of the study leader.

For a medium-sized chemical plant, where the total number of items to be considered is around 1200 pieces of equipment and piping, about 40 such meetings would be needed.[6] Various software programs are now available to assist in the management and scribing of the workshop.

Guidewords and parameters

edit

Source:[7]

In order to identify deviations, the team applies (systematically i.e. in a given order[a]) a set of guidewords to each node in the process. To prompt discussion, or to ensure completeness, appropriate process parameters are considered in turn, which apply to the design intent. Typical parameters are flow (or flowrate), temperature, pressure, level, composition, etc. The IEC standard notes guidewords should be chosen that are appropriate to the study, neither too specific (limiting ideas and discussion) nor too general (allowing loss of focus). A fairly standard set of guidewords (given as an example the standard) is as follows:

Guideword Meaning
No (not, none) None of the design intent is achieved
More (more of, higher) Quantitative increase in a parameter
Less (less of, lower) Quantitative decrease in a parameter
As well as (more than) An additional activity occurs
Part of Only some of the design intention is achieved
Reverse Logical opposite of the design intent occurs
Other than (other) Complete substitution (another activity takes place or an unusual activity occurs or uncommon condition exists)

Where a guide word is meaningfully applicable to a parameter (e.g., "no flow", "more temperature"), their combination should be recorded as a credible potential deviation from the design intent that requires review.

The following table gives an overview of commonly used guideword-parameter pairs (deviations) and common interpretations of them.

Parameter / Guide Word No More Less As well as Part of Reverse Other than
Flow no flow high flow low flow deviating concentration reverse flow
Pressure vacuum high pressure low pressure
Temperature high temperature low temperature
Level no level high level low level
Time sequence step skipped too long / too late too short / too soon extra actions missing actions backwards wrong time
Agitation no mixing fast mixing slow mixing
Reaction no reaction fast reaction / runaway slow reaction
Start-up / Shut-down too fast too slow actions missed wrong recipe
Draining / Venting none too long too short deviating pressure wrong timing
Inerting none high pressure low pressure contamination wrong material
Utility failure (e.g., instrument air, power) failure
DCS failure[b] failure
Maintenance none

Once the causes and effects of any potential hazards have been established, the system being studied can then be modified to improve its safety. The modified design should then be subject to a formal HAZOP close-out, to ensure that no new problems have been added.

HAZOP team

edit

A HAZOP study is a team effort. The team should be as small as practicable and having relevant skills and experience. Where a system has been designed by a contractor, the HAZOP team should contain personnel from both the contractor and the client company. A minimum team size of five[8] is recommended. In a large process there will be many HAZOP meetings and the individuals within the team may change, as different specialists and deputies will be required for the various roles. As many as 20 individuals may be involved.[2] Each team member should have a definite role as follows:[1]

Name Role
Study leader / Chairman / Facilitator Someone experienced in leading HAZOPs, who is familiar with this type of process but is independent of the design team. Responsible for progressing through the series of nodes, moderating the team discussions, maintaining the accuracy of the record, ensuring the clarity of the recommended actions and identifying appropriate actionees.
Recorder / secretary / scribe To document the causes, consequences, safeguards and actions identified for each deviation, to record the conclusions and recommendations of the team discussions (accurately but comprehensibly).
Design engineer To explain the design and its representation, to explains how a defined deviation can occur and the corresponding system or organizational response.
Operator / user Explains the operational context within which the system will operate, the operational consequences of a deviation and the extent to which deviations might lead to unacceptable consequences.
Specialists Provide expertise relevant to the system, the study, the hazards and their consequences. They could be called upon for limited participation.
Maintainer Someone who will maintain the system going forward.

In earlier publications it was suggested that the study leader could also be the recorder[2] but separate roles are now generally recommended.

The use of computers and projector screens enhances the recording of meeting minutes (the team can see what is minuted and ensure that it is accurate), the display of P&IDs for the team to review, the provision of supplemental documented information to the team and the logging of non-HAZOP issues that may arise during the review, e.g., drawing/document corrections and clarifications. Specialist software is now available from several suppliers to support the recording of meeting minutes and tracking the completion of recommended actions.

See also

edit

Notes

edit
  1. ^ If an individual team member spots a problem before the appropriate guideword is reached it may be possible to maintain rigid adherence to order; if most of the team wants to take the discussion out of order no great harm is done if they do, provided the study leader ensures that the secretary is not becoming too confused, and that all guidewords are (eventually) adequately considered
  2. ^ This relates to the Distributed Control System (DCS) hardware only. Software (unless specially carefully written) must be assumed to be capable of attempting incorrect or inopportune operation of anything under its control

References

edit
  1. ^ a b c d IEC (2016). Hazard and Operability Studies (HAZOP studies) – Application Guide. International Standard IEC 61882 (2.0 ed.). Genève: International Electrotechnical Commission. ISBN 978-2-8322-3208-8.
  2. ^ a b c d e Kletz, Trevor A. (1983). HAZOP & HAZAN. Notes on the Identification and Assessment of Hazards (2nd ed.). Rugby: IChemE.
  3. ^ Kletz, Trevor (2000). By Accident... A Life Preventing Them in Industry. PFV Publications. ISBN 0-9538440-0-5
  4. ^ Lawley, H.G. (1974). "Operability Studies and Hazard Analysis". Chemical Engineering Progress. 70(4): 105-116.
  5. ^ Chemical Industry Safety and Health Council (1977). A Guide to Hazard and Operability Studies. London: Chemical Industries Association
  6. ^ Swann, C. D.; Preston, M. L. (1995). "Twenty-five Years of HAZOPs". Journal of Loss Prevention in the Process Industries. 8(6): 349-353
  7. ^ Crawley, Frank; Tyler, Brian (2015). HAZOP: Guide to Best Practice (3rd ed.). Amsterdam, etc.: Elsevier. ISBN 978-0-323-39460-4.
  8. ^ Nolan, Dennis P. (1994) Application of HAZOP and What-If Safety Reviews to the Petroleum, Petrochemical and Chemical Industries. Park Ridge, N.J.: Noyes Publications. ISBN 0-8155-1353-4.

Further reading

edit