New York City Water Tunnel No. 3

New York City Water Tunnel No. 3 is a water-supply tunnel forming part of the New York City water supply system. It is being built by the New York City Department of Environmental Protection (NYCDEP) to provide New York City with a third connection to its upstate water supply. The tunnel will serve as a backup to Water Tunnel No. 1, completed in 1917, and Water Tunnel No. 2, completed in 1936.[1]

Water Tunnel No. 3 is the largest capital construction project in New York City history.[2] Construction began in 1970.[3] Portions of the tunnel were placed into service in 1998 and 2013 and the remaining sections are expected to be complete by 2032.[4][5]

The complete tunnel will be more than 60 miles (97 km) long, travel 500 feet (150 m) below street level in sections, and will cost over $6 billion.[4]

Stages

edit

The project was authorized in 1954 and imagined as "the greatest nondefense construction project in the history of Western Civilization".[6] The city determined that it needed a third water tunnel so that Tunnels 1 and 2 could be closed for inspection and repairs. Stage One construction of Tunnel 3 began in 1970 and completed in 1993. This portion was put into service in 1998 and cost about $1 billion.[3][7]

This first section was bored through bedrock between 250 and 800 feet (76 and 244 m) underground, using drilling and blasting techniques.[7] Section one is 13 miles (21 km) long and starts at Hillview Reservoir in Yonkers, New York then crosses under Central Park in Manhattan, to reach Fifth Avenue at 78th Street. From there it runs under the East River and Roosevelt Island into Astoria, Queens. It is a concrete-lined tunnel that is 24 feet (7.3 m) in diameter and reduces to 20 feet (6.1 m) in diameter before connecting to 14 vertical shafts.

 
Shafts connecting to Stage Two of the tunnel in Hudson Square, Lower Manhattan.

Stage Two was built using tunnel boring machines[7] and comprises two sections. The Brooklyn and Queens section runs 10 miles (16 km) and begins in Red Hook, Brooklyn, where it connects to the Richmond Tunnel for Staten Island. It passes through Park Slope, Bedford-Stuyvesant, and Bushwick before reaching Maspeth, Queens. From Maspeth it runs through Woodside and Astoria, where it connects to the end of the Stage One section. The Brooklyn section is 16 feet (4.9 m) in diameter, and the Queens section is 20 feet (6.1 m).[8]

The Manhattan section is 10 feet (3.0 m) in diameter and runs for 9 miles (14 km). It begins at a valve chamber in Central Park, runs south along the west side of Manhattan, and curves around the southern end of the island to come partway through the Lower East Side. A spur of the Manhattan tunnel begins on the west side at approximately 34th Street, goes to the east side and then turns north under Second Avenue to about 59th Street. The tunnel itself was completed in 2008, and after the construction of seven riser shafts was completed, this section of the tunnel opened in 2013.[2][3][9] Two additional riser shafts, each over 700 feet (210 m) deep, are under construction in Queens as of 2022.[10]

Three

edit

What used to be called Stage Three is now being referred to as a separate project, the "Kensico–City Tunnel". It will be 24 feet (7.3 m) in diameter, running from the Kensico Reservoir in Westchester to the Van Cortlandt Valve Chamber complex in the Bronx.[7]

Four

edit

Stage Four is a proposed tunnel that would start at the Hillview Reservoir in Yonkers, pass through the eastern Bronx and then through Queens, where it would eventually meet the Stage Two section.[7]

Valve chambers

edit

The largest valve chamber is in Van Cortlandt Park. It is built 250 feet (76 m) below the park surface. It controls the flow of water from the city's Catskill and Delaware systems. These systems provide 90 percent of the city's current drinking water. The Van Cortlandt Park Valve Chamber is 620 feet (190 m) long, 43 feet (13 m) wide and 41 feet (12 m) high. The complex has nine vertical shafts; and two manifolds. Each manifold is 560 feet (170 m) long and 24 feet (7.3 m) in diameter and is currently in operation.

Additional, though smaller, valve chambers are in use under Central Park at 79th Street, under Roosevelt Island, and in Jackson Heights.

Deaths

edit

Since 1970, when construction on the tunnel began, twenty-four people have died in construction-related accidents. The deaths have included twenty-three workers and a 12-year-old boy, Don-re Carroll, who fell 500 feet (150 m) to his death down a riser shaft while exploring uncapped water pipes in the Bronx.[3][11] No deaths have occurred since 1997.[2]

Construction progress

edit

In 2002, New York City mayor Michael Bloomberg made completion of the tunnel a priority, and set a goal date of 2021. Commissioner Christopher O. Ward helped move this project along for the Mayor.[6] A New York Times report in 2016 stated that mayor Bill de Blasio was postponing completion of the project indefinitely,[1] but he subsequently stated that this was a miscommunication between his press office and the Times, and that the completion date was actually being pushed up to 2020.[12][13] In 2017 De Blasio authorized city expenditures of $300 million for Tunnel No. 3, with an expected project completion date of 2025.[14]

Work on the final shafts for the tunnel began in 2021.[15] In September 2022 NYCDEP Commissioner Rohit Aggarwala stated that following the construction of the two deep riser shafts in Brooklyn and Queens, the Tunnel No. 3 project will be completed in 2032.[5]

References

edit
  1. ^ a b Dwyer, Jim (April 5, 2016). "De Blasio Postpones Work on Crucial Water Tunnel". The New York Times.
  2. ^ a b c Flegenheimer, Matt (October 16, 2013). "After Decades, a Water Tunnel Can Now Serve All of Manhattan". The New York Times.
  3. ^ a b c d Chan, Sewell (August 10, 2006). "Tunnelers Hit Something Big: A Milestone". The New York Times. It is the biggest public works project in New York City's history: a $6 billion water tunnel that has claimed 24 lives, endured under six mayors and survived three city fiscal crises, along with the falling and rising fortunes of the metropolis above it. ...
  4. ^ a b Kensinger, Nathan (April 22, 2021). "NYC's Giant Water Tunnel Begins Work On Final Shafts, Following 50 Years Of Construction". The Gothamist. Retrieved August 11, 2021.
  5. ^ a b "A Practical Perspective in Building Resilience into Urban Water Management by Commissioner Rohit T. Aggarwala". NYCDEP. September 20, 2022.
  6. ^ a b Grann, David (September 1, 2003). "City of Water". The New Yorker. Condé Nast. pp. 88–103.
  7. ^ a b c d e City Water Tunnel No. 3 Fact Sheet (PDF) (Report). NYC Department of Environmental Protection (NYCDEP). 2006. Archived from the original (PDF) on January 1, 2013. Retrieved October 21, 2013.
  8. ^ water-technology.net "New York City Tunnel No. 3, United States of America". Net Resources International. Retrieved December 15, 2011.
  9. ^ New York City 2008 Drinking Water Supply and Quality Report (PDF) (Report). NYCDEP. 2008. p. 6.
  10. ^ "Commissioner's Corner". NYCDEP. September 13, 2022.
  11. ^ Cohen, Noam S. (September 2, 1991). "Body of Bronx Boy Retrieved From a 500-Foot Shaft". The New York Times.
  12. ^ Engquist, Erik (April 6, 2016). "De Blasio does damage control in wake of New York Times' water-tunnel story". Crain's New York Business. Retrieved August 31, 2017.
  13. ^ "What's the real story behind the final phase of Water Tunnel No. 3?". New York Business Journal. Advance Publications Inc. April 6, 2016.
  14. ^ Giambusso, David (January 23, 2017). "De Blasio to allocate $300M for water tunnel". Politico.
  15. ^ Kensinger, Nathan (April 22, 2021). "NYC's Giant Water Tunnel Begins Work On Final Shafts, Following 50 Years Of Construction". Gothamist.
edit

40°53′38″N 73°53′24″W / 40.894°N 73.890°W / 40.894; -73.890